⚠️ Gas Supply Update – Kingsbridge, Devon

Our teams worked late into the night continuing efforts to restore gas supplies to customers impacted by the damage to our gas main.

This morning, engineers are already out in Kingsbridge, working through the remaining properties to restore supplies.

In Salcombe, commissioning of the gas main last night was successful, and our teams are also already in the area beginning the process of restoring supplies.


Please make every effort to be at your property today—this will greatly help speed up the process of getting homes back on gas.

We truly appreciate the support and cooperation shown by the community as we work to resolve the situation.

Engineers carry ID badges—verify by calling 0800 316 0478

Click here for the latest update. 

Skip to content

Wales & West Utilities completes gas investment near Yeovil

Posted: 23/07/2018

Wales & West Utilities is thanking the people of Tintinhull for their patience following the completion of gas pipe investment work in the village.

The £275,000 investment work involved upgrading over 1.2km of old metal pipes to new plastic ones in Church Street, Vicarage Road, St Margaret’s Road and Westfield Drove. It will make sure that local homes and businesses continue to receive a safe and reliable gas supply for years to come.

Wales & West Utilities worked closely with Somerset County Council to plan the work and keep disruption to a minimum.

Wales & West Utilities Programme Controller, Barry Sale, managed the work and said:

“This work was important to keep the gas flowing to heat homes and power businesses in the area and to make sure the gas network is fit for the future.

“We are delighted to have finished the work in a timely fashion and would like to thank those people that live and travel around the areas for their patience whilst it was ongoing.”