Upgrading the gas network in Devon
£1.2 million investment to upgrade gas network in south Paignton
Dates
27 Jul - Sept 26
Permit reference
WWU101
Upcoming

Wales & West Utilities is investing over £1.2 million over the next year to upgrade gas pipes in the south Paignton area, helping ensure a safe and reliable supply for communities in the area, for decades to come.

The intensive programme of mains replacement works will see the company replace over 7km of gas pipes across the area. To minimise disruption the gas emergency and pipeline service will work closely with Devon County Council to carefully plan projects and manage any necessary traffic measures.

The programme of mains replacement works will start in the Greenway Road area on 27 July and, all going to plan, this work will finish by 7 September. Further work will be undertaken in  the Cherry Brook Drive, Cliff Park Avenue, Dartmouth Road and Goodrington Road areas at a later date.

During the Greenway Road section of the project it has been agreed that the following traffic management will be in place:

Motorists will be asked to give and take during the following times:

27 July – 7 September:

  • Greenway Road, between the junctions of Dartmouth Road and Greenway Park

10 August – 7 September

  • Old Road, between the junctions of Greenway Road and Galmpton Farm Close
  • Galmpton Farm Close, at its junction with Old Road Close

Wales & West Utilities’ Natalie Raphael is managing the programme and said:

“We’re investing in our gas network to ensure it remains safe, reliable and fit for the future for the customers we serve across the area. We'll be keeping the local community updated on these works and working with the local authority, and other key partners, to keep disruption to a minimum.

“We understand our work can cause disruption, but it is essential to maintain a resilient gas network that households and business can rely on every day.

“While much of the gas network is out of sight, it plays a vital role in daily life – from heating homes to cooking meals and we know how important it is that gas is there when people need it.

“Once we’ve completed this intensive phase of work, we’ll leave behind an upgraded network that meets today’s energy needs, and is ready to transport greener gases in the future.

“By completing this work now, barring any emergency repairs, we can avoid returning to the area and causing further disruption to the local community for decades.”

For more information about work in your area, visit www.wwutilities.co.uk/gas-pipe-upgrade-projects/. As projects begin, customers can also find out what to expect from the work at www.wwutilities.co.uk/services/gas-pipe-upgrades/.

Wales & West Utilities is the gas emergency and pipeline service, delivering energy to over 7.5 million people across Wales and the south west of England. We don’t sell gas; we transport it through an extensive underground network of more than 35,000 kilometres of pipes.

If you smell gas or suspect carbon monoxide, call the National Gas Emergency number on 0800 111 999 immediately. Trained engineers are available 24/7 to respond and keep you safe.

Get in touch

Important Information

Our Customer Service Team is ready to take your call if you have any questions about our work. You can contact them on freephone 0800 912 2999.

Alternatively, you can contact us on X, formerly Twitter: WWUtilities or https://www.facebook.com/wwutilities.

Wales & West Utilities, the gas emergency and pipeline service, brings energy to 7.5m people across the south west of England and Wales. If you smell gas, or suspect the presence of carbon monoxide, call them on 0800 111 999 straight away, and engineers will be there to help any time of day or night.

Contact Us